Approx. Contract: $760,000.00
Laboratory

Scope of work: HVAC installation for lab facilities located on the 4th and 8th floors.

Hours: Total hours between labor, supervision, and fabrication 2,690. Job site crews are working four-10 hours shifts Monday through Thursday.
Total of 12,209 pounds and 2,700 linear feet of material

Equipment: Condensate piping, refrigerant piping, 22 VAV/VVT, 10 Loren Cook exhaust or supply fans, two Trane packaged 100% outside air Roof Top Units (RTUs) with factory mounted DDC controllers and sensors, one Trane Ductless Mini-Split Air Conditioning Unit with electric reheat,

Subcontractors include:
Trane for base building BAS Integration
Easy Way Insulation, Inc. for HVAC and plumbing insulation.
Addison Energy Technologies, LLC for testing and balancing