Vikor Scientific Upfit, 22 West Edge

Charleston, SC


Charleston, SC
Approx. Contract: $760,000.00
Laboratory

Scope of work:
HVAC installation for lab facilities located on the 4th and 8th floors.

Hours:
Total hours between labor, supervision, and fabrication — 2,690. Jobsite crews worked four 10-hours shifts Monday through Thursday.
Total of 12,209 pounds and 2,700 linear feet of material

Equipment:
Condensate piping, refrigerant piping:
22 VAV/VVT (variable air volume and variable volume and temperature):
Ten Loren Cook exhaust or supply fans”
Two Trane packaged 100% outside air roof top units (RTUs) with factory-mounted DDC controllers and sensors:
One Trane ductless mini-split air conditioning unit with electric reheat,

Subcontractors include:
Trane for base building BAS Integration:
Easy Way Insulation, Inc. for HVAC and plumbing insulation:
Addison Energy Technologies, LLC for testing and balancing: and
Baker Roofing.

.